Wednesday, March 4, 5:00 – 7:00 p.m.: Community Open House at the Amargosa Community Center, 1640 E. Farm Road, Amargosa, Nevada 89020
Balanced Rock Power and Rockview Dairies execute final land purchase option agreement for the Ponderosa Solar Project at the current Ponderosa Dairy site
Press release announcing option agreement with Rockview Dairy
Project-level stakeholder conversations initiated
Biological and cultural resource studies begin
Ponderosa Solar Project submits transmission line application to the BLM
Community Open House held at Amargosa Community Center, 1640 E. Farm Road, Amargosa, Nevada
Apply for Nye County Special Use Permit
Receive Nye County Special Use Permit approval
Receive BLM Finding of No Significant Impact (FONSI) for transmission line
Complete all remaining construction and building permits prior to construction
Commence construction
Commercial Operation Date (COD); begin operations